Several traffic pattern changes and road closures involving Wright Street started Monday, September 23, as Multimodal Corridor Enhancement (MCORE) Project 4 construction transitions from the east to the west side of the street.

A map showing the updated traffic patterns, pedestrian crossings, and parking adjustments is available. Please be aware of the following changes and seek alternate routes when traveling through the general area when practical.

Traffic Patterns/Road Closures

  • John Street, Daniel Street, and Chalmers Street will be closed to vehicular traffic where the roads intersect with Wright Street
  • Wright Street vehicular traffic will be one-way northbound on the east side of the street

Pedestrian Routes

  • Accessible pedestrian routes to the Main Quad across Wright Street will be located at John Street, Daniel Street, and Chalmers Street

Building Access/Parking Adjustments

  • Building access will be maintained at all times for facilities near the work area, although continuous north-south sidewalk access on the west side of Wright Street will be unavailable
  • Select parking spaces will be removed on Daniel Street